Buying from a developer
Compensation Calculator for Late Delivery of an Apartment
Is the developer late in delivering? The calculator works out the compensation set by the Sale (Apartments) Law, in the version that applies to your contract: the version for contracts signed on or after 7 July 2022, or the former version. The compensation is due without any need to prove damage.
Disclaimer: the calculator result is an estimate only, based on the data entered, and is not legal advice, tax advice or an assessment. Do not make a decision on the basis of the result alone. Use of the calculator is at the user's responsibility and subject to the terms of use and disclaimer.
How much compensation is due for late delivery?
In a contract signed from 7.7.2022, where the apartment was not delivered within one month of the contractual date, compensation is due without proof of damage, based on the rent of a comparable apartment: up to the end of the fourth month, the rent itself; then 1.25 times; and from the end of the tenth month, 1.5 times.
In a contract signed on or after 7 July 2022, if the apartment was not delivered within one month of the contractual date, the buyer is entitled to compensation without proof of damage. The compensation starts at the end of the first month and is calculated by reference to the rent of an apartment comparable in size and location: up to the end of the fourth month, the rent itself; from the end of the fourth month to the end of the tenth month, 1.25 times the rent; and from the end of the tenth month onwards, 1.5 times. If the contract sets higher compensation, the buyer is entitled to the higher of the two.
A worked example
A contract signed in March 2023. The contractual delivery date is 1 January 2026, and the apartment was actually delivered on 1 July 2026, a delay of six months. The rent of a comparable apartment is ₪6,000 a month.
- The first month, 1 to 31 January 2026: no compensation.
- The second to fourth months, 1 February to 30 April 2026: 3 months times ₪6,000 = ₪18,000.
- The fifth and sixth months, 1 May to 30 June 2026: 2 months times ₪7,500 (1.25 times) = ₪15,000.
Total: ₪33,000, without proof of damage. If the contract sets higher compensation for the same period, the buyer is entitled to the higher amount. The calculator on this page returns the same result for these figures.
And what if the contract was signed before 7 July 2022?
Then the former version of the section applies: entitlement arises only where the delay exceeds sixty days, and the compensation is then calculated from the contractual date, at 1.5 times the rent until the end of eight months and 1.25 times thereafter. The calculator selects the version according to the signing date you enter.
When is compensation not due?
Under the new version, the compensation does not apply if the delay was caused solely by an act or omission of the buyer, or by circumstances within section 18(a) of the Contracts (Remedies) Law. Under the old version, the parties could agree in the contract that the compensation would not apply to a delay resulting from circumstances beyond the seller's control. In many disputes this is the central question, so it is advisable to keep a record of your correspondence with the developer from the very first day of the delay.
How is the rent of a "comparable apartment" determined?
This is the one figure the calculator cannot know, so you enter it. In practice, it is compared with rental apartments of similar size and location, and in a dispute the amount is usually determined by an appraiser's opinion. Because the compensation is multiplied by the number of months, a small difference in the rent changes the total.
Part of a month: a full month or pro rata?
The law speaks of compensation "for each month or part thereof". The calculator shows both options: each part of a month counted as a full month, and a pro rata calculation by days. The difference is relatively small, but it is worth knowing that it exists.
Sources
- Sale (Apartments) Law, 5733-1973: section 5A, in the version for contracts made from 7 July 2022 and in the version for contracts made up to 6 July 2022. Hebrew.
- Contracts (Remedies for Breach of Contract) Law, 5731-1970: section 18(a) (force majeure or frustration). Hebrew.
The statutory text was checked on 23 October 2026.
A full explanation of the subject can be found in the article Late Delivery of an Apartment from a Developer.
More calculators: Purchase tax | Building Inputs linkage | Land appreciation tax | Additional costs | All calculators
Compensation for late delivery in a 30-second video

The video loads from YouTube only after you click. Go to the video page and transcript
In the video: A question we hear a lot: the contractor is late with delivery. Are we entitled to compensation? Yes. The Sale Law sets compensation without proof of damage. In a contract from 7.7.2022: from the end of one month after the contract date, based on the rent of a similar apartment, rising to 1.25 and then 1.5 times as the delay continues. The calculator on the site shows the amount.
Questions and answers
Do I need to prove damage to receive compensation for late delivery?
No. Compensation under section 5A of the Sale (Apartments) Law is awarded without proof of damage. A buyer who has suffered greater damage may claim it under the law of contracts.
From what date is the delay counted?
From the delivery date set in the contract. In a contract signed on or after 7 July 2022, compensation applies only if the delay exceeds one month, and it is paid from the end of the first month.
Can I receive both the compensation in the contract and the compensation under the law?
No. The buyer is entitled to compensation for late delivery either under the law or as set in the contract, whichever is higher.