Buying from a developer
Late delivery of a new apartment from a developer: when compensation is due and how much
The delivery date in the contract is almost always an optimistic one. The law sets out what the purchaser is entitled to when it is not met, including compensation for late delivery, and nothing in the contract can derogate from that.
First of all, what is your delivery date?
Contracts for buying from a developer set out the delivery date in several layers: a target date, a permitted period of postponement, and events that extend it. Before talking about compensation, you need to read the clause to the end and establish the exact contractual date from which the delay is counted. That is why the delivery clause is one of the most important clauses to review before signing.
The grace period: one month
Section 5A of the Sale (Apartments) Law establishes a statutory compensation mechanism. Following Amendment No. 9 to the Law, which came into force on 7 July 2022 and applies to agreements signed from that date, the grace period was shortened to one month. A delay of no more than one month does not give rise to compensation under the section. Beyond that, an entitlement to monthly compensation begins.
Compensation rates
Compensation is based on the rent for a similar apartment in size and location, and increases the longer the delay continues:
| Length of delay | Monthly compensation |
|---|---|
| Up to one month | No compensation under the section |
| From the end of the first month to the end of the fourth | 100% of the rent for a similar apartment |
| From the fifth month to the end of the tenth | 125% of the rent for a similar apartment |
| From the 11th month onwards | 150% of the rent for a similar apartment |
Compensation is paid for each month of delay and does not depend on proof of actual loss. In other words, even a purchaser who lived with family in the meantime and did not rent an apartment is entitled to it. However, the rent for a similar apartment has to be proved, and the burden is on the purchasers. And if the contract sets agreed compensation for delay, you receive the higher of the two, not both, as explained below.
When is the developer exempt from paying?
The law recognises situations in which the delay does not give rise to compensation, mainly where it was caused by an act or omission of the purchaser himself, or by external circumstances that the developer could not have foreseen and whose consequences he could not have prevented. This is in effect the rationale of the doctrine of frustration, and it is applied narrowly. Developers tend to stretch arguments of this kind, and not every such argument is accepted.
Note the other side of the coin as well: the purchaser himself may cause a delay, for example by ordering late changes or by paying late. Keeping orderly records of the dates of orders and payments protects you against such an argument. Late payment also costs money: in CC (Kfar Saba Magistrates) 25667-08-22 Malka v. Meshab (11 October 2026), the Court set off against the delay compensation default interest on a payment the buyers made eight months late.
What should you do right now?
Keep a signed copy of the contract and of every appendix, record in writing every change and payment, write to the developer when the delivery date approaches with no sign of completion, and collect data on the rent of similar apartments. On delivery, do not sign a waiver or a settlement without checking what you are giving up.
- Keep a signed copy of the contract and of every appendix, including the payment schedule and the specification
- Record in writing every change ordered, every payment and every confirmation received from the developer
- When the delivery date approaches and there is no sign of completion, write to the developer and ask for an updated date
- Collect data on the rent for similar apartments in the area as at the date the delay began
- Do not sign a waiver or a settlement at handover without checking what you are giving up
At handover, after years of waiting, it is easy to agree to any document put on the table just to get the keys. That is precisely where waivers of compensation that has already accrued are sometimes signed.
For contracts signed from 7 July 2022 the law protects you here too: a waiver, including in writing, of rights relating to late delivery, made a condition for handing over the apartment, is void (section 7A(b) of the Law). In earlier contracts this protection covers only waivers relating to defects, not the delay, so caution matters even more there.
Agreed compensation in the contract or statutory compensation: what do you get?
The higher of the two, not both. Section 5A of the Sale (Apartments) Law gives purchasers the rent-based compensation or the compensation agreed in the contract, "whichever is higher". A lower agreed amount, or a clause making the agreed compensation the sole remedy, does not reduce the statutory compensation.
The law sets a floor, not a ceiling. Under section 5A(a), purchasers are entitled to compensation based on the rent for a similar apartment in size and location, or to the compensation agreed in the contract for late delivery, whichever is higher. Under section 7A(a), the Law's provisions cannot be contracted out of except in the purchaser's favour. So a term capping compensation at a low amount, or adding exemptions the Law does not recognise, does not bind the purchasers.
This is what the Supreme Court held in LCA 6605/15 Shemesh v. Space (21 February 2016). The contract set agreed compensation of USD 700 a month and stated the buyers had no other remedy, and a further clause postponed delivery by at least 60 days if the buyers ordered changes, without setting a new date. The Court held that section 5A is mandatory, that such an open-ended postponement clause is in substance an exemption clause and therefore void, and that the buyers were entitled to be topped up to the statutory compensation.
On the other hand, an agreed postponement to a defined date is valid. The same judgment made clear that the parties may agree on a new delivery date, as a calendar date or a fixed period. In Malka v. Meshab the Court held that a change-order agreement in which the buyers agreed to postpone delivery by 45 days moved the contractual date, and the delay was counted from the new date. So before signing a changes rider, check whether it postpones delivery, and by how much.
When is the agreed compensation better? When it is higher. In CC (Tel Aviv Magistrates) 39845-10-21 Kanias Kami v. Bniya Asael Elad Investments (28 November 2022), a default judgment, the agreed compensation in the contract, 10% of the price, came to ILS 152,000, while compensation based on an appraiser's opinion came to ILS 142,583. The Court awarded the agreed compensation, as the higher figure, and not both. In CC (Jerusalem Magistrates) 4353-01-23 Morgenstern v. Prush (28 July 2026) the buyers neither pleaded nor proved the rent for a similar apartment, so they were awarded the contractual compensation of USD 1,000 a month, totalling ILS 295,700 for 84 months of delay.
Can you also get compensation for distress or further loss?
For the delay itself, usually not: the statutory or agreed compensation is meant to cover the loss caused by the delay, and the courts avoid double compensation. Further compensation is awarded in exceptional cases, or for a separate head of loss, such as defects in the apartment that was delivered.
In Kanias Kami the Court held that the compensation, whichever route is chosen, covers all loss from the delay, pecuniary and non-pecuniary, so no further award for distress was made. Morgenstern took a similar starting point, but because of an exceptional 11-year wait it also awarded ILS 20,000 for non-pecuniary loss.
The position is different for a different loss. In Malka v. Meshab the Court awarded compensation for the late delivery and, in addition, ILS 15,000 for distress caused by defects and damp in the apartment that was delivered. The Court explained this is not double compensation, because each head of loss relates to a different harm: the delay compensates for not receiving the apartment on time, and the distress award for living in a defective apartment. A purchaser claiming pecuniary loss beyond the compensation must prove it and its link to the breach, and show that it is not the same loss the compensation already covers.
Can you refuse to take an apartment with defects?
As a rule, no: defects that do not make the apartment unfit to live in do not justify refusal, so you take the apartment, record them in the protocol and demand repair. A material defect recorded in the protocol and raised in writing, such as no hot water, may be treated as if the apartment was not delivered, and the contract can widen the right to refuse.
As a rule, no. In CC (Tel Aviv Magistrates) 67099-05-18 Herzenstein v. Gindi (11 February 2021), the Court held that defects that do not make the apartment unfit to live in do not justify refusing delivery. In that case you take the apartment, record the defects in the delivery protocol and demand repair, and the delay compensation stops. But in the same case, an apartment with no hot water was treated as not delivered, even though the buyers had taken the keys, because the defect was recorded in the protocol and the buyers complained about it in writing. Two practical rules follow: record every material defect in the protocol, and complain in writing, not orally.
The contract itself can widen the right to refuse. In CA (Tel Aviv District) 17584-07-21 Azorim Binyan v. Ron (2 August 2022), the Court upheld a changes-rider clause allowing the buyers to refuse delivery if completion works required opening walls or lifting tiles.
A collapsed subcontractor, or a war: does it exempt the developer?
No. The Court held that the collapse of an executing contractor is a risk the seller bears, not a circumstance that exempts it, and also rejected an argument that a military operation delayed the works, because it was not proven to have actually caused the delay.
In Herzenstein the developer argued that the delay was caused by the collapse of an executing contractor. The Court held this is a risk the seller bears, not a circumstance that exempts it. An argument that a military operation delayed the works was also rejected, as it was not proven to have actually caused the delay. The Court further held that once the grace period was exceeded, compensation is calculated from the first day of the delay and not only from the end of the grace period, under the version of the Law that applied to that contract. For contracts signed from 7 July 2022 the wording differs: compensation starts one month after the contractual date (section 5A(a)).
Case law and sources
- Sale (Apartments) Law, 5733-1973: section 5A, in both versions.
- CC (Tel Aviv Magistrates) 67099-05-18 Herzenstein v. A. Gindi (11 February 2021).
- CA (Tel Aviv District) 17584-07-21 Azorim Binyan (1965) Ltd. v. Ron (2 August 2022).
- Sale (Apartments) Law: section 7A, no contracting out and void waivers.
- LCA 6605/15 Shemesh v. Space (21 February 2016).
- CC (Tel Aviv Magistrates) 39845-10-21 Kanias Kami v. Bniya Asael Elad Investments Ltd. (28 November 2022).
- CC (Jerusalem Magistrates) 4353-01-23 Morgenstern v. Prush (28 July 2026).
- CC (Kfar Saba Magistrates) 25667-08-22 Malka v. Meshab Housing, Building and Development Company Ltd. (11 October 2026).
The relevant chapters of the judgments were read in full and the texts checked against the sources on 28 October 2026.
Questions and answers
My contract was signed before July 2022. What applies to me?
Agreements signed before Amendment No. 9 came into force are governed by the previous version of section 5A, under which the grace period and the compensation rates are different. You should check the date of signing and the version that applies to it.
The developer claims the delay was caused by general delays in the industry. Does that exempt him?
Not every delay gives rise to an exemption. The exemption is intended for circumstances that could not have been foreseen and whose consequences could not have been prevented, and it is applied narrowly. A general argument about the state of the industry is not sufficient in itself.
The contract sets agreed compensation lower than the rent. What do I get?
The higher of the two. Section 5A of the Sale (Apartments) Law grants the rent-based compensation or the agreed compensation, whichever is higher, and this cannot be contracted out of to the purchaser's detriment. If the agreed compensation is higher, you get it, but not both.
I signed a changes rider that postpones delivery. Is it valid?
A postponement to a defined date, a calendar date or a fixed period, is generally valid, and the delay is counted from the new date. A clause postponing delivery without a clear date is treated as an exemption clause and is void (LCA 6605/15 Shemesh v. Space).
Can I also claim for distress or further loss beyond the monthly compensation?
For the delay itself, usually not: the statutory or agreed compensation also covers the distress caused by the delay. Further compensation is awarded in exceptional cases, such as a wait of many years, or for a separate loss such as defects in the apartment delivered, and further pecuniary loss must be proved.
Not sure the deal is safe? Let's start with a conversation
In an initial conversation we will go over the property, the other party and the payment schedule, and tell you what needs to be checked before you sign.